Home Construction Project
October 2021 - Present
Daniella and I have plans to build an apartment which would be our future and forever home in Arequipa, Peru. Where we live currently doesn’t give us the space to grow as a family or the ability to provide hospitality for those we serve. For someone who loves connecting with people, this is absolutely BRUTAL! We will be building a third floor on Daniella's parent’s house. We would have a separate entrance from the street and our own staircase at the front of the house to give us complete independence.
The Timetable
We are just getting started, but here's what we expect.
October & November 2021 - Architect Plans
December & January 2022 - Engineering Plans
February & March 2022 - Finalize Plans
April & May 2022 - Municipal Paperwork
August 2022 - Begin Construction
The Budget
As of October 5th, we have a construction budget! It's a little over $ per square meter ($ per square foot) and at the moment we think we're going to be at square meters. That's roughly 1,500 square feet and the above price includes all 3rd floor construction, labor, and finishing touches.
Approx: $
The number above doesn't include the following:
1) Architect & engineer's wages
2) Municipality paperwork & Licenses
3) Concrete stairs leading up to our floor
4) Private entrance from the street
5) First floor dividing wall, greenery, and gate that separates us from the main house.
6) Earthquake reinforcement
Approx: $
Of course these numbers could fluctuate a little bit, but we are confident in this budget moving forward and are excited to see how the Lord will bring this project to fruition! If you would like to help us reach our $ goal of building a house and having a ministry home base, the give link below will take you to the World Indigenous Missions giving page where you can make a donation. You can find us listed as number 299 or Jones, C in the Long-Term Missionaries section. For additional information on how to serve alongside us, scroll up and click on the Partnership and Get Involved tabs.
October 2021 - Present
Daniella and I have plans to build an apartment which would be our future and forever home in Arequipa, Peru. Where we live currently doesn’t give us the space to grow as a family or the ability to provide hospitality for those we serve. For someone who loves connecting with people, this is absolutely BRUTAL! We will be building a third floor on Daniella's parent’s house. We would have a separate entrance from the street and our own staircase at the front of the house to give us complete independence.
The Timetable
We are just getting started, but here's what we expect.
October & November 2021 - Architect Plans
December & January 2022 - Engineering Plans
February & March 2022 - Finalize Plans
April & May 2022 - Municipal Paperwork
August 2022 - Begin Construction
The Budget
As of October 5th, we have a construction budget! It's a little over $ per square meter ($ per square foot) and at the moment we think we're going to be at square meters. That's roughly 1,500 square feet and the above price includes all 3rd floor construction, labor, and finishing touches.
Approx: $
The number above doesn't include the following:
1) Architect & engineer's wages
2) Municipality paperwork & Licenses
3) Concrete stairs leading up to our floor
4) Private entrance from the street
5) First floor dividing wall, greenery, and gate that separates us from the main house.
6) Earthquake reinforcement
Approx: $
Of course these numbers could fluctuate a little bit, but we are confident in this budget moving forward and are excited to see how the Lord will bring this project to fruition! If you would like to help us reach our $ goal of building a house and having a ministry home base, the give link below will take you to the World Indigenous Missions giving page where you can make a donation. You can find us listed as number 299 or Jones, C in the Long-Term Missionaries section. For additional information on how to serve alongside us, scroll up and click on the Partnership and Get Involved tabs.